A) A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting this TV at the WACC.
B) A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV) , then compounding this PV to find the IRR.
C) If a project's IRR is greater than the WACC, then its NPV must be negative.
D) To find a project's IRR, we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
E) To find a project's IRR, we must find a discount rate that is equal to the WACC.
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
B) You should recommend that the project be rejected because, although its NPV is positive, it has an IRR that is less than the WACC.
C) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs, in this case it would be better to focus on the MIRR, which exceeds the WACC. You should explain this to the president and tell him that that the firm's value will increase if the project is accepted.
D) You should recommend that the project be rejected because (1) its NPV is positive and (2) it has two IRRs, one of which is less than the WACC, which indicates that the firm's value will decline if the project is accepted.
E) You should recommend that the project be rejected because, although its NPV is positive, its MIRR is less than the WACC, and that indicates that the firm's value will decline if it is accepted.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR.
D) If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR.
E) To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
Multiple Choice: Problems
Correct Answer
verified
Multiple Choice
A) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount, which the NPV method provides.
B) The discounted payback method eliminates all of the problems associated with the payback method.
C) When evaluating independent projects, the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
D) To find the MIRR, we discount the TV at the IRR.
E) A project's NPV profile must intersect the X-axis at the project's WACC.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) If the WACC is 10%, both projects will have positive NPVs.
B) If the WACC is 6%, Project S will have the higher NPV.
C) If the WACC is 13%, Project S will have the lower NPV.
D) If the WACC is 10%, both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer
verified
Multiple Choice
A) 1.86 years
B) 2.07 years
C) 2.30 years
D) 2.53 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) $5.47
B) $6.02
C) $6.62
D) $7.29
E) $7.82
Correct Answer
verified
Multiple Choice
A) 1.91 years
B) 2.12 years
C) 2.36 years
D) 2.59 years
E) 2.85 years
Correct Answer
verified
Multiple Choice
A) 2.03 years
B) 2.25 years
C) 2.50 years
D) 2.75 years
E) 3.03 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14.05%
B) 15.61%
C) 17.34%
D) 19.27%
E) 21.20%
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method versus the NPV is that the IRR does not take account of cash flows over a project's full life.
B) One defect of the IRR method versus the NPV is that the IRR does not take account of the time value of money.
C) One defect of the IRR method versus the NPV is that the IRR does not take account of the cost of capital.
D) One defect of the IRR method versus the NPV is that the IRR values a dollar received today the same as a dollar that will not be received until sometime in the future.
E) One defect of the IRR method versus the NPV is that the IRR does not take proper account of differences in the sizes of projects.
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
E) If the NPV is negative, the IRR must also be negative.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 12.55%
B) 13.21%
C) 13.87%
D) 14.56%
E) 15.29%
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 107
Related Exams