A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 9.70%
B) 10.78%
C) 11.98%
D) 13.31%
E) 14.64%
Correct Answer
verified
Multiple Choice
A) Project D probably has a higher IRR.
B) Project D is probably larger in scale than Project C.
C) Project C probably has a faster payback.
D) Project C probably has a higher IRR.
E) The crossover rate between the two projects is below 12%.
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
C) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
D) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.42 years
B) 1.58 years
C) 1.75 years
D) 1.93 years
E) 2.12 years
Correct Answer
verified
Multiple Choice
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) 14.08%
B) 15.65%
C) 17.21%
D) 18.94%
E) 20.83%
Correct Answer
verified
Multiple Choice
A) 2.31 years
B) 2.56 years
C) 2.85 years
D) 3.16 years
E) 3.52 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 12.55%
B) 13.21%
C) 13.87%
D) 14.56%
E) 15.29%
Correct Answer
verified
Multiple Choice
A) -$18.89
B) -$19.88
C) -$20.93
D) -$22.03
E) -$23.13
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting this TV at the WACC.
B) A project's regular IRR is found by discounting the cash inflows at the WACC to find the present value (PV) , then compounding this PV to find the IRR.
C) If a project's IRR is greater than the WACC, then its NPV must be negative.
D) To find a project's IRR, we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
E) To find a project's IRR, we must find a discount rate that is equal to the WACC.
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
B) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.
C) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
D) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
E) Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC) , these two methods always rank mutually exclusive projects in the same order.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) -$59.03
B) -$56.08
C) -$53.27
D) -$50.61
E) -$48.08
Correct Answer
verified
Showing 61 - 80 of 85
Related Exams