A) If the WACC is 10%,both projects will have positive NPVs.
B) If the WACC is 6%,Project S will have the higher NPV.
C) If the WACC is 13%,Project S will have the lower NPV.
D) If the WACC is 10%,both projects will have a negative NPV.
E) Project S's NPV is more sensitive to changes in WACC than Project L's.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
B) You should recommend that the project be rejected because,although its NPV is positive,it has an IRR that is less than the WACC.
C) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs,in this case it would be better to focus on the MIRR,which exceeds the WACC.You should explain this to the president and tell him that that the firm's value will increase if the project is accepted.
D) You should recommend that the project be rejected because (1) its NPV is positive and (2) it has two IRRs,one of which is less than the WACC,which indicates that the firm's value will decline if the project is accepted.
E) You should recommend that the project be rejected because,although its NPV is positive,its MIRR is less than the WACC,and that indicates that the firm's value will decline if it is accepted.
Correct Answer
verified
Multiple Choice
A) If the WACC is 13%,Project A's NPV will be higher than Project B's.
B) If the WACC is 9%,Project A's NPV will be higher than Project B's.
C) If the WACC is 6%,Project B's NPV will be higher than Project A's.
D) If the WACC is greater than 14%,Project A's IRR will exceed Project B's.
E) If the WACC is 9%,Project B's NPV will be higher than Project A's.
Correct Answer
verified
Multiple Choice
A) $6.49
B) $9.40
C) $0.00
D) $7.66
E) $6.66
Correct Answer
verified
Multiple Choice
A) ?More of Project A's cash flows occur in the later years.
B) ?More of Project B's cash flows occur in the later years.
C) ?We must have information on the cost of capital in order to determine which project has the larger early cash flows.
D) ?The NPV profile graph is inconsistent with the statement made in the problem.
E) The crossover rate,i.e. ,the rate at which Projects A and B have the same NPV,is greater than either project's IRR.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If a project's IRR is equal to its WACC,then,under all reasonable conditions,the project's NPV must be negative.
B) If a project's IRR is equal to its WACC,then under all reasonable conditions,the project's IRR must be negative.
C) If a project's IRR is equal to its WACC,then under all reasonable conditions the project's NPV must be zero.
D) There is no necessary relationship between a project's IRR,its WACC,and its NPV.
E) When evaluating mutually exclusive projects,those projects with relatively long lives will tend to have relatively high NPVs when the cost of capital is relatively high.
Correct Answer
verified
Multiple Choice
A) For a project with normal cash flows,any change in the WACC will change both the NPV and the IRR.
B) To find the MIRR,we first compound cash flows at the regular IRR to find the TV,and then we discount the TV at the WACC to find the PV.
C) The NPV and IRR methods both assume that cash flows can be reinvested at the WACC.However,the MIRR method assumes reinvestment at the MIRR itself.
D) If two projects have the same cost,and if their NPV profiles cross in the upper right quadrant,then the project with the higher IRR probably has more of its cash flows coming in the later years.
E) If two projects have the same cost,and if their NPV profiles cross in the upper right quadrant,then the project with the lower IRR probably has more of its cash flows coming in the later years.
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
B) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC,whereas IRR assumes that cash flows are reinvested at the IRR.The NPV assumption is generally more appropriate.
C) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
D) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
E) Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC) ,these two methods always rank mutually exclusive projects in the same order.
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC,the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's,then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC,the project must have a positive NPV.
E) If the NPV is negative,the IRR must also be negative.
Correct Answer
verified
Multiple Choice
A) 1.62 years
B) 1.58 years
C) 1.15 years
D) 1.47 years
E) 1.24 years
Correct Answer
verified
Multiple Choice
A) 1.28 years
B) 1.58 years
C) 1.83 years
D) 1.62 years
E) 1.49 years
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV,IRR,MIRR,and discounted payback (using a payback requirement of 3 years or less) methods always lead to the same accept/reject decisions for independent projects.
B) For mutually exclusive projects with normal cash flows,the NPV and MIRR methods can never conflict,but their results could conflict with the discounted payback and the regular IRR methods.
C) Multiple IRRs can exist,but not multiple MIRRs.This is one reason some people favor the MIRR over the regular IRR.
D) If a firm uses the discounted payback method with a required payback of 4 years,then it will accept more projects than if it used a regular payback of 4 years.
E) The percentage difference between the MIRR and the IRR is equal to the project's WACC.
Correct Answer
verified
Multiple Choice
A) 12.69%
B) 13.98%
C) 15.58%
D) 18.15%
E) 16.07%
Correct Answer
verified
Multiple Choice
A) Project S.
B) Project L.
C) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
D) Neither project is sensitive to changes in the discount rate,since both have NPV profiles that are horizontal.
E) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
Correct Answer
verified
Multiple Choice
A) 14.45%
B) 12.92%
C) 12.57%
D) 11.28%
E) 11.75%
Correct Answer
verified
Multiple Choice
A) 9.64%
B) 10.82%
C) 12.58%
D) 11.29%
E) 11.76%
Correct Answer
verified
Multiple Choice
A) The MIRR and NPV decision criteria can never conflict.
B) The IRR method can never be subject to the multiple IRR problem,while the MIRR method can be.
C) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
D) The higher the WACC,the shorter the discounted payback period.
E) The MIRR method assumes that cash flows are reinvested at the crossover rate.
Correct Answer
verified
Showing 21 - 40 of 107
Related Exams