A) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
B) You should recommend that the project be rejected because, although its NPV is positive, it has an IRR that is less than the WACC.
C) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs, in this case it would be better to focus on the MIRR, which exceeds the WACC. You should explain this to the president and tell him that the firm’s value will increase if the project is accepted.
D) You should recommend that the project be rejected. Although its NPV is positive it has two IRRs, one of which is less than the WACC, which indicates that the firm’s value will decline if the project is accepted.
E) You should recommend that the project be rejected because, although its NPV is positive, its MIRR is less than the WACC, and that indicates that the firm’s value will decline if it is accepted.
Correct Answer
verified
Multiple Choice
A) 1.86 years
B) 2.07 years
C) 2.30 years
D) 2.53 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) Project S.
B) Project L.
C) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
D) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
E) The solution cannot be determined because the problem gives us no information that can be used to determine the projects' relative IRRs.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
B) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.
C) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
D) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
E) Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC) , these two methods always rank mutually exclusive projects in the same order.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If the WACC is 13%, Project A's NPV will be higher than Project B's.
B) If the WACC is 9%, Project A's NPV will be higher than Project B's.
C) If the WACC is 6%, Project B's NPV will be higher than Project A's.
D) If the WACC is greater than 14%, Project A's IRR will exceed Project B's.
E) If the WACC is 9%, Project B's NPV will be higher than Project A's.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 2.08%
B) 2.31%
C) 2.57%
D) 2.82%
E) 3.10%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) $54.62
B) $57.49
C) $60.52
D) $63.54
E) $66.72
Correct Answer
verified
Multiple Choice
A) Lacks an objective, market-determined benchmark for making decisions.
B) Ignores cash flows beyond the payback period.
C) Does not directly account for the time value of money.
D) Does not provide any indication regarding a project's liquidity or risk.
E) Does not take account of differences in size among projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.88 years
B) 2.09 years
C) 2.29 years
D) 2.52 years
E) 2.78 years
Correct Answer
verified
Multiple Choice
A) For a project to have more than one IRR, then both IRRs must be greater than the WACC.
B) If two projects are mutually exclusive, then they are likely to have multiple IRRs.
C) If a project is independent, then it cannot have multiple IRRs.
D) Multiple IRRs can occur only if the signs of the cash flows change more than once.
E) If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project S because it has the higher IRR and will continue to have the higher IRR even at the new WACC.
Correct Answer
verified
Multiple Choice
A) -$59.03
B) -$56.08
C) -$53.27
D) -$50.61
E) -$48.08
Correct Answer
verified
Multiple Choice
A) The MIRR and NPV decision criteria can never conflict.
B) The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
C) One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
D) The higher the WACC, the shorter the discounted payback period.
E) The MIRR method assumes that cash flows are reinvested at the crossover rate.
Correct Answer
verified