A) 13.42%
B) 14.91%
C) 16.56%
D) 18.22%
E) 20.04%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The crossover rate for the two projects must be less than 12%.
B) Assuming the timing pattern of the two projects' cash flows is the same, Project B probably has a higher cost (and larger scale) .
C) Assuming the two projects have the same scale, Project B probably has a faster payback than Project A.
D) The crossover rate for the two projects must be 12%.
E) Since B has the higher IRR, then it must also have the higher NPV if the crossover rate is less than the WACC of 12%.
Problems
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
E) If the NPV is negative, the IRR must also be negative.
Correct Answer
verified
Multiple Choice
A) The crossover rate must be less than 10%.
B) The crossover rate must be greater than 10%.
C) If the WACC is 8%, Project X will have the higher NPV.
D) If the WACC is 18%, Project Y will have the higher NPV.
E) Project X is larger in the sense that it has the higher initial cost.
Correct Answer
verified
Multiple Choice
A) The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
B) The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
C) The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
D) The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
E) The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's IRR increases as the WACC declines.
B) A project's NPV increases as the WACC declines.
C) A project's MIRR is unaffected by changes in the WACC.
D) A project's regular payback increases as the WACC declines.
E) A project's discounted payback increases as the WACC declines.
Correct Answer
verified
Multiple Choice
A) The regular payback method recognizes all cash flows over a project's life.
B) The discounted payback method recognizes all cash flows over a project's life, and it also adjusts these cash flows to account for the time value of money.
C) The regular payback method was, years ago, widely used, but virtually no companies even calculate the payback today.
D) The regular payback is useful as an indicator of a project's liquidity because it gives managers an idea of how long it will take to recover the funds invested in a project.
E) The regular payback does not consider cash flows beyond the payback year, but the discounted payback overcomes this defect.
Correct Answer
verified
Multiple Choice
A) The NPV, IRR, MIRR, and discounted payback (using a payback requirement of 3 years or less) methods always lead to the same accept/reject decisions for independent projects.
B) For mutually exclusive projects with normal cash flows, the NPV and MIRR methods can never conflict, but their results could conflict with the discounted payback and the regular IRR methods.
C) Multiple IRRs can exist, but not multiple MIRRs. This is one reason some people favor the MIRR over the regular IRR.
D) If a firm uses the discounted payback method with a required payback of 4 years, then it will accept more projects than if it used a regular payback of 4 years.
Correct Answer
verified
Multiple Choice
A) -$18.89
B) -$19.88
C) -$20.93
D) -$22.03
E) -$23.13
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Project S.
B) Project L.
C) Both projects are equally sensitive to changes in the WACC since their NPVs are equal at all costs of capital.
D) Neither project is sensitive to changes in the discount rate, since both have NPV profiles that are horizontal.
Correct Answer
verified
Multiple Choice
A) $41.25
B) $45.84
C) $50.93
D) $56.59
E) $62.88
Correct Answer
verified
Multiple Choice
A) $54.62
B) $57.49
C) $60.52
D) $63.54
E) $66.72
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) If the WACC is 13%, Project A's NPV will be higher than Project B's.
B) If the WACC is 9%, Project A's NPV will be higher than Project B's.
C) If the WACC is 6%, Project B's NPV will be higher than Project A's.
D) If the WACC is greater than 14%, Project A's IRR will exceed Project B's.
E) If the WACC is 9%, Project B's NPV will be higher than Project A's.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 104
Related Exams