A) One drawback of the regular payback is that this method does not take account of cash flows beyond the payback period.
B) If a project's payback is positive,then the project should be accepted because it must have a positive NPV.
C) The regular payback ignores cash flows beyond the payback period,but the discounted payback method overcomes this problem.
D) One drawback of the discounted payback is that this method does not consider the time value of money,while the regular payback overcomes this drawback.
E) The shorter a project's payback period,the less desirable the project is normally considered to be by this criterion.
Correct Answer
verified
Multiple Choice
A) A project's regular IRR is found by discounting the cash inflows at the cost of capital to find the present value (PV) ,then compounding this PV to find the IRR.
B) If a project's IRR is greater than the WACC,then its NPV must be negative.
C) To find a project's IRR,we must solve for the discount rate that causes the PV of the inflows to equal the PV of the project's costs.
D) To find a project's IRR,we must find a discount rate that is equal to the cost of capital.
E) A project's regular IRR is found by compounding the cash inflows at the cost of capital to find the terminal value (TV) ,then discounting this TV at the cost of capital.
Correct Answer
verified
Multiple Choice
A) One defect of the IRR method is that it does not take account of the time value of money.
B) One defect of the IRR method is that it does not take account of the cost of capital.
C) One defect of the IRR method is that it values a dollar received today the same as a dollar that will not be received until sometime in the future.
D) One defect of the IRR method is that it assumes that the cash flows to be received from a project can be reinvested at the IRR itself,and that assumption is often not valid.
E) One defect of the IRR method is that it does not take account of cash flows over a project's full life.
Correct Answer
verified
Multiple Choice
A) If the cost of capital is 6%,Project S will have the higher NPV.
B) If the cost of capital is 13%,Project S will have the lower NPV.
C) If the cost of capital is 10%,both projects will have a negative NPV.
D) Project S's NPV is more sensitive to changes in cost of capital than Project L's.
E) If the cost of capital is 10%,both projects will have positive NPVs.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) A project's NPV increases as the cost of capital declines.
B) A project's MIRR is unaffected by changes in the cost of capital.
C) A project's regular payback increases as the cost of capital declines.
D) A project's discounted payback increases as the cost of capital declines.
E) A project's IRR increases as the cost of capital declines.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) One drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money.
B) If a project's payback is positive,then the project should be rejected because it must have a negative NPV.
C) The regular payback ignores cash flows beyond the payback period,but the discounted payback method overcomes this problem.
D) If a company uses the same payback requirement to evaluate all projects,say it requires a payback of 4 years or less,then the company will tend to reject projects with relatively short lives and accept long-lived projects,and this will cause its risk to increase over time.
E) The longer a project's payback period,the more desirable the project is normally considered to be by this criterion.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 1.42 years
B) 1.58 years
C) 1.75 years
D) 1.93 years
E) 2.12 years
Correct Answer
verified
Multiple Choice
A) The discounted payback method eliminates all of the problems associated with the payback method.
B) When evaluating independent projects,the NPV and IRR methods often yield conflicting results regarding a project's acceptability.
C) To find the MIRR,we discount the TV at the IRR.
D) A project's NPV profile must intersect the X-axis at the project's cost of capital.
E) The IRR method appeals to some managers because it gives an estimate of the rate of return on projects rather than a dollar amount,which the NPV method provides.
Correct Answer
verified
Multiple Choice
A) 1.61 years
B) 1.79 years
C) 1.99 years
D) 2.22 years
E) 2.44 years
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because,although its NPV is positive,it has an IRR that is less than the cost of capital.
B) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs,in this case it would be better to focus on the MIRR,which exceeds the cost of capital.You should explain this to the president and tell him that the firm's value will increase if the project is accepted.
C) You should recommend that the project be rejected.Although its NPV is positive it has two IRRs,one of which is less than the cost of capital,which indicates that the firm's value will decline if the project is accepted.
D) You should recommend that the project be rejected because,although its NPV is positive,its MIRR is less than the cost of capital,and that indicates that the firm's value will decline if it is accepted.
E) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the cost of capital.
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B,then Project A must also have a higher NPV.
B) The IRR calculation implicitly assumes that all cash flows are reinvested at the cost of capital.
C) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
D) If a project has normal cash flows and its IRR exceeds its cost of capital,then the project's NPV must be positive.
E) If Project A has a higher IRR than Project B,then Project A must have the lower NPV.
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects,even if this means that a competitor might come in and capture this market.
B) You should recommend Project R,because at the new cost of capital it will have the higher NPV.
C) You should recommend Project K,because at the new cost of capital it will have the higher NPV.
D) You should recommend Project K because it has the higher IRR and will continue to have the higher IRR even at the new cost of capital.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the cost of capital,whereas IRR assumes that cash flows are reinvested at the IRR.The NPV assumption is generally more appropriate.
B) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
C) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
D) Since cash flows under the IRR and MIRR are both discounted at the same rate (the cost of capital) ,these two methods always rank mutually exclusive projects in the same order.
E) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Assuming the timing pattern of the two projects' cash flows is the same,Project B probably has a higher cost (and larger scale) .
B) Assuming the two projects have the same scale,Project B probably has a faster payback than Project A.
C) The crossover rate for the two projects must be 12%.
D) Since B has the higher IRR,then it must also have the higher NPV if the crossover rate is less than the cost of capital of 12%.
E) The crossover rate for the two projects must be less than 12%.
Correct Answer
verified
Showing 61 - 80 of 80
Related Exams