A) $28,939
B) $30,462
C) $32,066
D) $33,753
E) $35,530
Correct Answer
verified
Multiple Choice
A) interest on funds borrowed to help finance the project.
B) the end-of-project recovery of any working capital required to operate the project.
C) cannibalization effects, but only if those effects increase the project's projected cash flows.
D) expenditures to date on research and development related to the project, provided those costs have already been expensed for tax purposes.
E) all costs associated with the project that have been incurred prior to the time the analysis is being conducted.
Correct Answer
verified
Multiple Choice
A) differential project risk cannot be accounted for by using "risk-adjusted discount rates" because it is highly subjective and difficult to justify. it is better to not risk adjust at all.
B) other things held constant, if returns on a project are thought to be positively correlated with the returns on other firms in the economy, then the project's npv will be found using a lower discount rate than would be appropriate if the project's returns were negatively correlated.
C) monte carlo simulation uses a computer to generate random sets of inputs, those inputs are then used to determine a trial npv, and a number of trial npvs are averaged to find the project's expected npv. sensitivity and scenario analyses, on the other hand, require much more information regarding the input variables, including probability distributions and correlations among those variables. this makes it easier to implement a simulation analysis than a scenario or a sensitivity analysis, hence simulation is the most frequently used procedure.
D) dcf techniques were originally developed to value passive investments (stocks and bonds) . however, capital budgeting projects are not passive investmentsσmanagers can often take positive actions after the investment has been made that alter the cash flow stream. opportunities for such actions are called real options. real options are valuable, but this value is not captured by conventional npv analysis. therefore, a project's real options must be considered separately.
E) the firm's corporate, or overall, wacc is used to discount all project cash flows to find the projects' npvs. then, depending on how risky different projects are judged to be, the calculated npvs are scaled up or down to adjust for differential risk.
Correct Answer
verified
Multiple Choice
A) since the firm's director of capital budgeting spent some of her time last year to evaluate the new project, a portion of her salary for that year should be charged to the project's initial cost.
B) the company has spent and expensed $1 million on r&d associated with the new project.
C) the company spent and expensed $10 million on a marketing study before its current analysis regarding whether to accept or reject the project.
D) the firm would borrow all the money used to finance the new project, and the interest on this debt would be $1.5 million per year.
E) the new project is expected to reduce sales of one of the company's existing products by 5%.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) $20,762
B) $21,854
C) $23,005
D) $24,155
E) $25,363
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) an example of an externality is a situation where a bank opens a new office, and that new office causes deposits in the bank's other offices to decline.
B) the npv method automatically deals correctly with externalities, even if the externalities are not specifically identified, but the irr method does not. this is another reason to favor the npv.
C) both the npv and irr methods deal correctly with externalities, even if the externalities are not specifically identified. however, the payback method does not.
D) identifying an externality can never lead to an increase in the calculated npv.
E) an externality is a situation where a project would have an adverse effect on some other part of the firm's overall operations. if the project would have a favorable effect on other operations, then this is not an externality.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) project x has more corporate (or within-firm) risk than project y.
B) project x has more market risk than project y.
C) project x has the same level of corporate risk as project y.
D) project x has less market risk than project y.
E) project x has more stand-alone risk than project y.
Correct Answer
verified
Multiple Choice
A) if the building could be sold, then the after-tax proceeds that would be generated by any such sale should be charged as a cost to any new project that would use it.
B) this is an example of an externality, because the very existence of the building affects the cash flows for any new project that rowell might consider.
C) since the building was built in the past, its cost is a sunk cost and thus need not be considered when new projects are being evaluated, even if it would be used by those new projects.
D) if there is a mortgage loan on the building, then the interest on that loan would have to be charged to any new project that used the building.
E) since the building has been paid for, it can be used by another project with no additional cost. therefore, it should not be reflected in the cash flows for any new project.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 61 - 78 of 78
Related Exams