Filters
Question type

Study Flashcards

Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows: Standard and actual costs for direct materials for the manufacture of 1,000 units of product were as follows:    Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance. Determine the (a) quantity variance, (b) price variance, and (c) total direct materials cost variance.

Correct Answer

verifed

verified

Ruby Company produces a chair that requires 5 yds. of material per unit. The standard price of one yard of material is $7.50. During the month, 8,500 chairs were manufactured, using 43,600 yards at a cost of $7.55 per yard. Determine the (a) price variance, (b) quantity variance, and (c) cost variance.

Correct Answer

verifed

verified

(a) Price variance = ($7.50 - ...

View Answer

Using the following information, prepare a factory overhead flexible budget for Andover Company where the total factory overhead cost is $75,500 at normal capacity (100%). Include capacity at 75%, 90%, 100%, and 110%. Total variable cost is $6.25 per unit and total fixed costs are $38,000. The information is for month ended August 31, 2012. (Hint: Determine units produced at normal capacity.)

Correct Answer

verifed

verified

The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,548,000. Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. Compute the material price variance.


A) 0
B) 59,400U
C) 59,400F
D) 6,000U

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The Lucy Corporation purchased and used 129,000 board feet of lumber in production, at a total cost of $1,548,000. Original production had been budgeted for 22,000 units with a standard material quantity of 5.7 board feet per unit and a standard price of $12 per board foot. Actual production was 23,500 units. Compute the material quantity variance.


A) 63,000F
B) 63,000U
C) 59,400F
D) 59,400U

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

If a company records inventory purchases at standard cost and also records purchase price variances, prepare the journal entry for a purchase of 6,000 widgets that were bought at $8.00 and have a standard cost of $8.15.

Correct Answer

verifed

verified

Oak Company produces a chair that requires 6 yds. of material per unit. The standard price of one yard of material is $7.50. During the month, 8,500 chairs were manufactured, using 48,875 yards. Journalize the entry to record the standard direct materials used in production.

Correct Answer

verifed

verified

Changes in technology, machinery, or production methods may make past cost data irrelevant when setting standards.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct materials costs for November: The following data relate to direct materials costs for November:   What is the direct materials quantity variance? A)  $3,600 favorable B)  $1,240 favorable C)  $3,600 unfavorable D)  $1,240 unfavorable What is the direct materials quantity variance?


A) $3,600 favorable
B) $1,240 favorable
C) $3,600 unfavorable
D) $1,240 unfavorable

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period: The following data relate to direct labor costs for the current period:   What is the direct labor time variance? A)  $ 4,500 favorable B)  $18,000 unfavorable C)  $ 3,600 favorable D)  $17,100 favorable What is the direct labor time variance?


A) $ 4,500 favorable
B) $18,000 unfavorable
C) $ 3,600 favorable
D) $17,100 favorable

E) None of the above
F) All of the above

Correct Answer

verifed

verified

The total manufacturing cost variance consists of:


A) Direct materials price variance, direct labor cost variance, and fixed factory overhead volume variance
B) Direct materials cost variance, direct labor rate variance, and factory overhead cost variance
C) Direct materials cost variance, direct labor cost variance, variable factory overhead controllable variance
D) Direct materials cost variance, direct labor cost variance, factory overhead cost variance

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

In most businesses, cost standards are established principally by accountants.

A) True
B) False

Correct Answer

verifed

verified

The principle of exceptions allows managers to


A) focus on correcting variances between standard costs and actual costs.
B) focus on correcting variances between variable costs and actual costs.
C) focus on correcting variances between competitor's costs and actual costs.
D) focus on correcting variances between competitor's costs and standard costs.

E) None of the above
F) All of the above

Correct Answer

verifed

verified

The following data is given for the Stringer Company: The following data is given for the Stringer Company:   Overhead is applied on standard labor hours. The direct material quantity variance is: A)  22,800F B)  22,800U C)  52,000F D)  52,000U Overhead is applied on standard labor hours. The direct material quantity variance is:


A) 22,800F
B) 22,800U
C) 52,000F
D) 52,000U

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Which of the following is not a reason standard costs are separated in two components?


A) the price and quantity variances need to be identified separately to correct the actual major differences.
B) identifying variances determines which manager must find a solution to major discrepancies.
C) if a negative variance is over-shadowed by a favorable variance, managers may overlook potential corrections.
D) variances brings attention to discrepancies in the budget and requires managers to revise budgets closer to actual.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A favorable cost variance occurs when actual cost is less than budgeted cost at actual volumes.

A) True
B) False

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual was 800 units at $12, the direct materials price variance was $800 favorable.

A) True
B) False

Correct Answer

verifed

verified

A favorable cost variance occurs when


A) Actual costs are more than standard costs.
B) Standard costs are more than actual costs.
C) Standard costs are less than actual costs.
D) None of the above.

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Which of the following conditions normally would not indicate that standard costs should be revised?


A) The engineering department has revised product specifications in responding to customer suggestions.
B) The company has signed a new union contract which increases the factory wages on average by $5.00 an hour.
C) Actual costs differed from standard costs for the preceding week.
D) The world price of raw materials increased.

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

Japan Company produces lamps that require 2.25 standard hours per unit at an hourly rate of $15.00 per hour. If 7,700 units required 19,250 hours at an hourly rate of $14.90 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance?

Correct Answer

verifed

verified

(a) Rate variance = ($15.00 - $14.90) x ...

View Answer

Showing 121 - 140 of 160

Related Exams

Show Answer