A) If Project A's IRR exceeds Project B's, then A must have the higher NPV.
B) A project's MIRR can never exceed its IRR.
C) If a project with normal cash flows has an IRR less than the WACC, the project must have a positive NPV.
D) If the NPV is negative, the IRR must also be negative.
E) If a project with normal cash flows has an IRR greater than the WACC, the project must also have a positive NPV.
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
B) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
C) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
D) If a project has normal cash flows and its IRR exceeds its WACC, then the project's NPV must be positive.
E) If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
B) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
C) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
D) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
E) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
Correct Answer
verified
Multiple Choice
A) 12.55%
B) 13.21%
C) 13.87%
D) 14.56%
E) 15.29%
Correct Answer
verified
Multiple Choice
A) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
B) You should recommend Project R, because at the new WACC it will have the higher NPV.
C) You should recommend Project K, because at the new WACC it will have the higher NPV.
D) You should recommend Project K because it has the higher IRR and will continue to have the higher IRR even at the new WACC.
E) You should reject both projects because they will both have negative NPVs under the new conditions.
Correct Answer
verified
Multiple Choice
A) The NPV method assumes that cash flows will be reinvested at the risk-free rate, while the IRR method assumes reinvestment at the IRR.
B) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the risk-free rate.
C) The NPV method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
D) The IRR method does not consider all relevant cash flows, particularly cash flows beyond the payback period.
E) The NPV method assumes that cash flows will be reinvested at the WACC, while the IRR method assumes reinvestment at the IRR.
Correct Answer
verified
Multiple Choice
A) 9.43%
B) 9.91%
C) 10.40%
D) 10.92%
E) 11.47%
Correct Answer
verified
Multiple Choice
A) One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR.The NPV assumption is generally more appropriate.
B) One advantage of the NPV over the MIRR method is that NPV takes account of cash flows over a project's full life whereas MIRR does not.
C) One advantage of the NPV over the MIRR method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
D) Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC) , these two methods always rank mutually exclusive projects in the same order.
E) One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project's full life whereas IRR does not.
Correct Answer
verified
Multiple Choice
A) $32.12
B) $35.33
C) $38.87
D) $40.15
E) $42.16
Correct Answer
verified
Multiple Choice
A) If the WACC is 9%, Project A's NPV will be higher than Project B's.
B) If the WACC is 6%, Project B's NPV will be higher than Project A's.
C) If the WACC is greater than 14%, Project A's IRR will exceed Project B's.
D) If the WACC is 9%, Project B's NPV will be higher than Project A's.
E) If the WACC is 13%, Project A's NPV will be higher than Project B's.
Correct Answer
verified
Multiple Choice
A) $265.65
B) $278.93
C) $292.88
D) $307.52
E) $322.90
Correct Answer
verified
Multiple Choice
A) 13.13%
B) 14.44%
C) 15.89%
D) 17.48%
E) 19.22%
Correct Answer
verified
Multiple Choice
A) $77.49
B) $81.56
C) $85.86
D) $90.15
E) $94.66
Correct Answer
verified
Multiple Choice
A) More of Project B's cash flows occur in the later years.
B) We must have information on the cost of capital in order to determine which project has the larger early cash flows.
C) The NPV profile graph is inconsistent with the statement made in the problem.
D) The crossover rate, i.e., the rate at which Projects A and B have the same NPV, is greater than either project's IRR.
E) More of Project A's cash flows occur in the later years.
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The higher the WACC used to calculate the NPV, the lower the calculated NPV will be.
B) If a project's NPV is greater than zero, then its IRR must be less than the WACC.
C) If a project's NPV is greater than zero, then its IRR must be less than zero.
D) The NPVs of relatively risky projects should be found using relatively low WACCs.
E) A project's NPV is generally found by compounding the cash inflows at the WACC to find the terminal value (TV) , then discounting the TV at the IRR to find its PV.
Correct Answer
verified
Multiple Choice
A) 2.31 years
B) 2.56 years
C) 2.85 years
D) 3.16 years
E) 3.52 years
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 108
Related Exams